Top News
Next Story
Newszop

Waaree Energies to supply 900 MW of modules for Solar Power Plant in Rajasthan

Send Push
Waaree Energies on Monday said it has secured a contract from Serentica Renewables India to supply 900 megawatts (MW) modules for a project located at Fatehgarh in the Jaisalmer district of Rajasthan.

The project is expected to be one of the largest solar power plants installed in India with Waaree modules, marking a milestone for both companies, the company said.

The delivery schedule for these Top-Con bifacial modules is set from August 2024 to February 2025.

Waaree Energies will oversee the comprehensive manufacturing, testing, packing, and transportation of these solar PV modules, ensuring adherence to the quality standards and timely project execution.

Sunil Rathi, Director of Sales, Waaree Energies Ltd. said, "Our elite series modules are expected to contribute to the efficiency, durability, and performance of this project. Moreover, our company has been deploying multiple projects in Rajasthan and Gujarat, thereby contributing to the clean energy shift in these states."

Waaree Energies Ltd. will oversee the comprehensive manufacturing, testing, packing, and transportation of these solar PV modules, ensuring adherence to the quality standards and timely execution of the project. The deployment of this project is expected to increase the region's renewable energy capacity and contribute to reducing carbon emissions and promoting environmental sustainability, the company said.

Waaree Energies has an aggregate installed capacity of 12 GW, as of June 30, 2023. It commenced operations in 2007 focusing on solar PV module manufacturing and has four solar module manufacturing facilities in India, with an international presence.
Loving Newspoint? Download the app now